Project
Milestone Schedule
| June
2004 |
Draft
Environmental Impact Report 588 (DEIR 588) for
the RELOOC Strategic Plan - Olinda Alpha Landfill
Implementation was released June 17, 2004 for
a 45-day public comment period.
|
| November
17, 2004 |
Public Hearing:
Proposed Final Environmental Impact Report submitted
to County Planning Commission. County Planning
Commission recommended that the Board of Supervisors
find Proposed Environmental Impact Report adequate
environmental documentation for the RELOOC Strategic
Plan implementation at the Olinda Alpha Landfill.
|
| April 17, 2007 |
Proposed Final Environmental Impact Report certified by County Board of Supervisors. |
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
|